    Physical Achievements

    Programme/Scheme wise Cumulative Physical Progress as on 30th November, 2025

    Sector FY 2025-26 Achievements during the Month of November, 2025 FY 2025-26 Achievements (1st April 2025-30th November2025) Cumulative Achievements (as on 30.11.2025)
    Installed RE Capacity (Capacities in MW)
    Solar Power* 2924.42 27201.79 132848.25
    Wind Power 386.10 3948.20 53986.02
    Biomass (Bagasse) Cogeneration 0.00 0.00 9821.32
    Biomass(non-bagasse)Cogeneration 0.00 14.20 935.99
    Waste to Energy 0.00 0.00 309.34
    Waste to Energy (off-grid) 1.00 16.41 547.28
    Small Hydro Power 0.00 58.06 5158.61
    Sub Total (Exc. Large Hydro) 3311.52 31238.66 203606.81
    Large Hydro^ 0.00 2620.00 50348.17
    Total RE 3311.52 33858.66 253954.98
    Nuclear Power# 0.00 700.00 8780.00
    Total Non-Fossil 3311.52 34558.66 262734.98

    Solar Power* (Cumulative) : 132.85 GW

    • Ground Mounted Solar Plant : 100.80 GW
    • Grid Connected Solar Rooftop: 23.16 GW
    • Hybrid Projects(Solar Component) : 3.34 GW
    • Off-Grid Solar: 5.55 GW

    ^Large Hydro includes 6925.6 MW Pumped Storage

    # Excluding Nuclear Capacity of 100 MW, which is under outage for very long time, and have been removed temporarily w.e.f. 31.05.2025