A A+ A- facebook twitter youtube

Green Energy Corridor

Printer-friendly version

Green Energy Corridor

 

 Introduction

For evacuation of large scale renewable energy, Intra State Transmission System (InSTS) project was sanctioned by the Ministry in FY 2015-16. It is being implemented by eight renewable rich States of Tamil Nadu, Rajasthan, Karnataka, Andhra Pradesh, Maharashtra, Gujarat, Himachal Pradesh and Madhya Pradesh. The project is being implemented in these States by the respective State Transmission Utilities (STUs).

The project includes about approx. 9400 ckm transmission lines and Substations of total capacity of approx. 19000 MVA to be completed by March 2020. The purpose is to evacuate approx. 20,000 MW of large scale renewable power and improvement of the grid in the implementing States.

The total project cost is approx. Rs. 10141 crores. The funding mechanism consists of 40% from Government of India Grant (total Rs. 4056.67 crores), 20% from State Equity and 40% from loan from KfW, Germany (500 million EUR).

The Central grant is disbursed in two installments to the STUs: a) 70% Advance on the award of contract, and b) Balance 30% after successful commissioning and three months performance testing.

 

Institutional Arrangements & Implementation Strategy

The project is being implemented by respective State Transmission Utilities (STUs) which allot the work through competitive bidding process. The Ministry monitors the project every month. A Project Appraisal Committee under chairmanship of concerned Joint Secretary and with members from CEA & PGCIL monitors the project & recommends on the disbursal of central grant to the STUs.

 

Attachments:

a. Administrative approval

b. Fund disbursal guidelines

c. Revised sanction to the States along with list of projects.