State Electricity Regulatory Commissions (SERCs) are determining preferential tariffs

Printer-friendly version

POLICIES INTRODUCED BY THE STATE GOVERNMENTS /SERC’s REGULATIONS FOR WIND POWER PROJECTS

                                                                                                                                                                                                        (As on September, 2014)

 

Andhra Pradesh*

 

Karnataka*

Madhya Pradesh*

Maharashtra*

Rajasthan*

Tamil-nadu*

Gujarat*

Wheeling and Transmission

As per Rules, Regulations and terms and conditions as approved by the Commission.

5 %

of energy

Allowed

2% of energy + transmission charges as per ERC

Normal Open Access Charges

Normal Open Access Charges

5% of

Energy in case of consumption at HV / EHV and 7.5% in case of LV

Normal OA Transmission Charges and transmission losses for 66 kV and above

 

Normal OA Transmission Charges and 10.0% as transmission and wheeling losses for below than 66 kV

Banking

Allowed

Allowed @ 2%  of energy input

Allowed

15 Minutes Adjustment

6 Months

5%

(12 months)

Monthly settlement

Buy-back (Rs./Unit)

 

 4.70

 

4.20

 5.92

#

Rs. 5.93 /unit for Jaisalmer, Barmer and Jodhpur etc. and Rs. 5.64 /unit for other district

3.51 (Levelised)

4.15

Open Access transaction

Allowed

Allowed

Allowed

Allowed

Allowed

Allowed

Allowed

RPO

5.0%

7% - 10%

Captive & Open Access -5%

 

14-15- 7.00%

 

14-15- 9.00%

15-16- 9.00%

     2014-15 – 9.00%

     2015-16 – 10.20%

     2016-17 – 11.40%^

9.00%

2014-15 – 8.00%

2015-16 – 9.00%

   2016-17 – 10.00%$

*Policy announced by State Electricity Regulatory Commission in the respective State.

# The Tariff is as follows

Particular

Net Levellised Tariff (FY 2013-14)

Wind Zone – 1

5.70

Wind Zone – 2

5.01

Wind Zone – 3

4.18

Wind Zone – 4

3.92

$ - Bifurcation of RPO

Financial Year

Obligation expressed as % of energy consumption

Total

Wind

Solar

Other

2014-15

8.00

6.25

1.25%

0.50%

2015-16

9.00

7.00

1.50%

0.50%

2016-17

10.00

7.75

1.75%

0.50%

^ - Bifurcation of RPO

Financial Year

Obligation expressed as % of energy consumption

Total

Wind

Solar

Other

2014-15

9.00

6.80

1.50%

0.70%

2015-16

10.20

7.30

2.00%

0.90%

2016-17

11.40

7.80

2.50%

1.10%